Project Progress
Lumpini Place UD-Posri
Project progress as of Date 30 November 2014
Project Information
Lumpini Place UD-Posri
Category Condominium
Number of floors 14 stories high residential condominium (3 buildings, 6 Towers) Location Udonthani
Area 22.50 - 98.50 sq.m. Status Ready to move
Description Forecast/Actual Complete %
Piling Works 3.37% 3.37%
Structural works 35.09% 35.09%
Architectural Works 34.23% 34.23%
Electrical Works 11.20% 11.20%
Plumbing Works 5.88% 5.88%
 Elevator Works  3.02% 3.02%
 Cabinet Works  7.21% 7.21%
Summary 100 % 100 %