Project Progress
Project progress as of Date 31 January 2014
Project Information
Category
Number of floors Location
Area Status
Description Forecast/Actual Complete %
Piling Works 9 % 9 %
Structural works 26 % 26 %
Architectural Works 41 % 41 %
Electrical Works 11 % 11 %
Plumbing Works 6 % 6 %
 Elevator Works  1 % 1 %
 Cabinet Works  6 % 6 %
Summary 100 % 100 %