The Selected Kaset-Ngamwongwan by LPN
ความคืบหน้าโครงการ

The Selected Kaset-Ngamwongwan by LPN

Project progress as of
15 September 2018
 
Description Forecast/Actual Complete %
Piling Works 5 % 5 %
Structural works 27 % 27 %
Architectural Works 41 % 41 %
Electrical Works 12 % 12 %
Plumbing Works 8 % 8 %
Elevator Works 2 % 2 %
Cabinet Works 2 % 2 %
Air Conditionner Works 3 % 3 %
Summary 100 % 100 %






























 
Perspective

Perspective

Perspective

Perspective

Perspective

Perspective

 
Perspective

Perspective

Structural work 100% complete

Structural work 100% complete

Structural work 100% complete

Structural work 100% complete

Structural work 100% complete

Structural work 100% complete

Architectural Works

Architectural Works

Elevator Works

Elevator Works

Lobby

Lobby

Learning Zone

Learning Zone

 
Juristic Person Office

Juristic Person Office

Fitness Room

Fitness Room

Fitness Room

Fitness Room

Electrical Works

Electrical Works

Electrical Works

Electrical Works

Electrical Works

Electrical Works

Electrical Works

Electrical Works

Electrical Works

Electrical Works

 
Plumping Works

Plumping Works

Plumping Works

Plumping Works

Plumping Works

Plumping Works

Plumping Works

Plumping Works

Plumping Works

Plumping Works

Landscape of the swimming pool on the 5th floor

Landscape of the swimming pool on the 5th floor

Landscape of the swimming pool on the 5th floor

Landscape of the swimming pool on the 5th floor

Infinity Garden on the 19th floor

Infinity Garden on the 19th floor

 
Infinity Garden on the 19th floor

Infinity Garden on the 19th floor

Project entrance

Project entrance

Architectural Works

Architectural Works

Street Basketball

Street Basketball

Architectural Works

Architectural Works

Landscape on the 1st floor

Landscape on the 1st floor

Landscape on the 1st floor

Landscape on the 1st floor