Lumpini Ville Sukhumvit 76 (2)
ความคืบหน้าโครงการ

Lumpini Ville Sukhumvit 76 (2)

Project progress as of
28 February 2019
 
Description Forecast/Actual Complete %
Piling Works 4 % 4 %
Structural works 24 % 24 %
Architectural Works 41 % 41 %
Electrical Works 10 % 10 %
Plumbing Works 6 % 6 %
Elevator Works 1 % 1 %
Cabinet Works 10 % 10 %
Air Conditionner Works 4 % 4 %
Summary 100 % 100 %