Lumpini Ville Phattanakan - Srinakarin
ความคืบหน้าโครงการ

Lumpini Ville Phattanakan - Srinakarin

Project progress as of
15 January 2020
 
Description Forecast/Actual Complete %
Piling Works 6 % 4 %
Structural works 37 % 9 %
Architectural Works 24 % 2 %
Electrical Works 12 % 1 %
Plumbing Works 7 % 1 %
Elevator Works 2 % 0 %
Cabinet Works 9 % 0 %
Air Conditionner Works 3 % 0 %
Summary 100 % 17 %