Lumpini Ville Phattanakan - Srinakarin
ความคืบหน้าโครงการ

Lumpini Ville Phattanakan - Srinakarin

Project progress as of
31 July 2020
 
Description Forecast/Actual Complete %
Piling Works 4 % 4 %
Structural works 34 % 34 %
Architectural Works 26 % 23 %
Electrical Works 13 % 10 %
Plumbing Works 7 % 6 %
Elevator Works 2 % 1 %
Cabinet Works 11 % 10 %
Air Conditionner Works 3 % 2 %
Summary 100 % 90 %










 
Architectural Work

Architectural Work