Lumpini Ville Phattanakan - Srinakarin
ความคืบหน้าโครงการ

Lumpini Ville Phattanakan - Srinakarin

Project progress as of
30 September 2020
 
Description Forecast/Actual Complete %
Piling Works 4 % 4 %
Structural works 34 % 34 %
Architectural Works 26 % 26 %
Electrical Works 13 % 13 %
Plumbing Works 7 % 7 %
Elevator Works 2 % 2 %
Cabinet Works 11 % 11 %
Air Conditionner Works 3 % 3 %
Summary 100 % 100 %