Lumpini-Ville-Naklua-Wongamat
ความคืบหน้าโครงการ

Lumpini-Ville-Naklua-Wongamat

Project progress as of
31 January 2014
 
Description Forecast/Actual Complete %
Piling Works 5 % 5 %
Structural works 32 % 32 %
Architectural Works 36 % 36 %
Electrical Works 13 % 13 %
Plumbing Works 8 % 8 %
 Elevator Works  2 % 2 %
 Cabinet Works  4 % 4 %
Summary 100 % 100 %