Lumpini Township Rangsit-Klong 1
ความคืบหน้าโครงการ

Lumpini Township Rangsit-Klong 1

Project progress as of
31 March 2019
 
Description Forecast/Actual Complete %
Piling Works 2.58% 2.58%
Structural works 26.07% 26.07%
Architectural Works 44.87% 44.87%
Electrical Works 13.99% 13.99%
Plumbing Works 7.63% 7.63%
Elevator Works 2% 2%
Cabinet Works 2.86% 2.86%
Summary 100% 100%













 