Lumpini Suite Din Daeng - Ratchaprarop
ความคืบหน้าโครงการ

Lumpini Suite Din Daeng - Ratchaprarop

Project progress as of
30 November 2018
 
Description Forecast/Actual Complete %
Piling Works 4 % 4 %
Structural works 37 % 37 %
Architectural Works 33 % 33 %
Electrical Works 10 % 10 %
Plumbing Works 7 % 7 %
Elevator Works 2 % 2 %
Cabinet Works 4 % 4 %
Air Conditionner Works 3 % 3 %
Summary 100 % 100 %





 
Perspective

Perspective

Structural Works

Structural Works

Architectural Works

Architectural Works

 
Architectural Works

Architectural Works

Cabinet Works

Cabinet Works

Architectural Works

Architectural Works

Electrical Works

Electrical Works

Air Conditionner Works

Air Conditionner Works

Plumbing Works

Plumbing Works

Land Scape

Land Scape

Swimming pool landscape work on the 7th floor

Swimming pool landscape work on the 7th floor

 
Landscape work on the 27th floor and 30th floor

Landscape work on the 27th floor and 30th floor

Landscape work on the 27th floor and 30th floor

Landscape work on the 27th floor and 30th floor