Lumpini Selected Sutthisan - Saphan-Khwai
ความคืบหน้าโครงการ

Lumpini Selected Sutthisan - Saphan-Khwai

Project progress as of
31 October 2019
 
Description Forecast/Actual Complete %
Piling Works 4 % 4 %
Structural works 29 % 29 %
Architectural Works 32 % 32 %
Electrical Works 10 % 10 %
Plumbing Works 7 % 7 %
Elevator Works 2 % 2 %
Cabinet Works 13 % 13 %
Air Conditionner Works 3 % 3 %
Summary 100 % 100 %































 