Lumpini Place Taopoon Interchange
ความคืบหน้าโครงการ

Lumpini Place Taopoon Interchange

Project progress as of
31 March 2021
 
Description Forecast/Actual Complete %
Piling Works 4 % 4 %
Structural works 30 % 14 %
Architectural Works 38 % 10 %
Electrical Works 13 % 2 %
Plumbing Works 8 % 2 %
Elevator Works 2 % 0 %
Cabinet Works 2 % 0 %
Air Conditionner Works 3 % 0 %
Summary 100 % 32 %









 
Architectural Work on the 8th floor

Architectural Work on the 8th floor

Electrical Works on the 9th floor

Electrical Works on the 9th floor