Lumpini Place Rama3 - Riverine
ความคืบหน้าโครงการ

Lumpini Place Rama3 - Riverine

Project progress as of
15 January 2020
 
Description Forecast/Actual Complete %
Piling Works 6 % 6 %
Structural works 31 % 31 %
Architectural Works 38 % 32 %
Electrical Works 13 % 12 %
Plumbing Works 8 % 7 %
Elevator Works 2 % 1 %
Cabinet Works 2 % 2 %
Summary 100 % 91 %



















 
Architectural  Work

Architectural Work

Electrical  Work

Electrical Work

Electrical  Work

Electrical Work