Lumpini Park Phahon 32
ความคืบหน้าโครงการ

Lumpini Park Phahon 32

Project progress as of
15 October 2019
 
Description Forecast/Actual Complete %
Piling Works 4 % 4 %
Structural works 27 % 27 %
Architectural Works 42 % 27 %
Electrical Works 12 % 10 %
Plumbing Works 7 % 6 %
Elevator Works 2 % 1 %
Cabinet Works 3 % 2 %
Air Conditionner Works 3 % 2 %
Summary 100 % 79 %