Lumpini Park Borom Ratchachonni - Sirindhorn
ความคืบหน้าโครงการ

Lumpini Park Borom Ratchachonni - Sirindhorn

Project progress as of
15 January 2020
 
Description Forecast/Actual Complete %
Piling Works 4 % 3 %
Structural works 41 % 15 %
Architectural Works 30 % 3 %
Electrical Works 9 % 1 %
Plumbing Works 7 % 0 %
Elevator Works 3 % 0 %
Cabinet Works 33 % 0 %
Air Conditionner Works 3 % 0 %
Summary 100 % 22 %





















 
Perspective

Perspective

Structural Works on the 7th and 8th floor - Building C

Structural Works on the 7th and 8th floor - Building C

Structural Works on the 7th and 8th floor - Building C

Structural Works on the 7th and 8th floor - Building C

 
Structural Works on the 5th and 6th floor - Building B

Structural Works on the 5th and 6th floor - Building B

Structural Works on the 5th and 6th floor - Building B

Structural Works on the 5th and 6th floor - Building B

Structural Works on the 5th and 6th floor - Building A

Structural Works on the 5th and 6th floor - Building A

Structural Works on the 5th and 6th floor - Building A

Structural Works on the 5th and 6th floor - Building A

Architectural Work on the 1st floor - Building B

Architectural Work on the 1st floor - Building B