Lumpini Ville Chaengwattana 10
ความคืบหน้าโครงการ

Lumpini Ville Chaengwattana 10

Project progress as of
31 March 2021
 
Description Forecast/Actual Complete %
Piling Works 3 % 3 %
Structural works 31 % 2 %
Architectural Works 41 % 0 %
Electrical Works 13 % 0 %
Plumbing Works 8 % 0 %
Elevator Works 1 % 0 %
Cabinet Works 3 % 0 %
Summary 100 % 5 %












 