ความคืบหน้าโครงการ

Lumpini Ville Sukhumvit 101/1-Punnavithi

Project progress as of
30 November 2020
 
Description Forecast/Actual Complete %
Piling Works 5 % 5 %
Structural works 31 % 31 %
Architectural Works 40 % 40 %
Electrical Works 13 % 13 %
Plumbing Works 7 % 7 %
Elevator Works 2 % 2 %
Cabinet Works 2 % 2 %
Summary 100 % 100 %