Lumpini Ville Sukhumvit 101/1-Punnavithi
ความคืบหน้าโครงการ

Lumpini Ville Sukhumvit 101/1-Punnavithi

Project progress as of
16 November 2020
 
Description Forecast/Actual Complete %
Piling Works 5 % 5 %
Structural works 31 % 30 %
Architectural Works 40 % 32 %
Electrical Works 13 % 12 %
Plumbing Works 7 % 6 %
Elevator Works 2 % 2 %
Cabinet Works 2 % 1 %
Summary 100 % 88 %




 