Lumpini Ville Prachachuen-Phongphet 2
ความคืบหน้าโครงการ

Lumpini Ville Prachachuen-Phongphet 2

Project progress as of
30 September 2014
 
Description Forecast/Actual Complete %
Piling Works 8 % 8 %
Structural works 25 % 25 %
Architectural Works 39 % 39 %
Electrical Works 12 % 12 %
Plumbing Works 8 % 8 %
 Elevator Works  2 % 2 %
 Cabinet Works  6 % 6 %
Summary 100 % 100 %