The Selected Kaset-Ngamwongwan by LPN
ความคืบหน้าโครงการ

The Selected Kaset-Ngamwongwan by LPN

Project progress as of
15 April 2018
 
Description Forecast/Actual Complete %
Piling Works 3 % 3 %
Structural works 30 % 21 %
Architectural Works 39 % 3 %
Electrical Works 13 % 2 %
Plumbing Works 8 % 1 %
Elevator Works 2 % 0 %
Cabinet Works 3 % 0 %
Air Conditionner Works 2 % 0 %
Summary 100 % 30 %




















 
Perspective

Perspective

Structural work of the flooring on the 15th floor

Structural work of the flooring on the 15th floor

Structural work of the swimming pool

Structural work of the swimming pool

 
Architectural Works on the 1st floor

Architectural Works on the 1st floor

Architectural Works on the 5th floor

Architectural Works on the 5th floor

Electrical Works on the 14th floor

Electrical Works on the 14th floor

Electrical Works on the 11th floor

Electrical Works on the 11th floor

Plumping Works on the 10, 14th floor

Plumping Works on the 10, 14th floor