Lumpini Ville Sukhumvit 76 - Bearing
ความคืบหน้าโครงการ

Lumpini Ville Sukhumvit 76 - Bearing

Project progress as of
15 March 2017
 
Description Forecast/Actual Complete %
Piling Works 6 % 6 %
Structural works 30 % 30 %
Architectural Works 30 % 30 %
Electrical Works 14 % 14 %
Plumbing Works 8 % 8 %
 Elevator Works  2 % 2 %
 Cabinet Works  10 % 10 %
Summary 100 % 100%












 