Lumpini Ville Ratchaphruek-Bang Waek
ความคืบหน้าโครงการ

Lumpini Ville Ratchaphruek-Bang Waek

Project progress as of
15 May 2017
 
Description Forecast/Actual Complete %
Piling Works 2.46 % 2.46 %
Structural works 28.95 % 28.95 %
Architectural Works 33.44 % 33.44 %
Electrical Works 15.40 % 15.40 %
Plumbing Works 9.87 % 9.87 %
 Elevator Works  1.57 % 1.57 %
 Cabinet Works  8.30 % 8.30 %
Summary 100 % 100 %









 