Lumpini Ville Ratburana - River View 2
ความคืบหน้าโครงการ

Lumpini Ville Ratburana - River View 2

Project progress as of
28 February 2018
 
Description Forecast/Actual Complete %
Piling Works 4 % 4 %
Structural works 30 % 30 %
Architectural Works 36 % 36 %
Electrical Works 14 % 14 %
Plumbing Works 10 % 10 %
Elevator Works 2 % 2 %
Cabinet Works 4 % 4 %
Summary 100 % 100 %















 