Lumpini ville onnut 46
ความคืบหน้าโครงการ

Lumpini ville onnut 46

Project progress as of
31 October 2014
 
Description Forecast/Actual Complete %
Piling Works 4% 4%
Structural works 28% 28%
Architectural Works 36% 36%
Electrical Works 13% 13%
Plumbing Works 8% 8%
 Elevator Works  2% 2%
 Cabinet Works  9% 9%
Summary 100 % 100 %