Lumpini Ville On Nut-Lat Krabang
ความคืบหน้าโครงการ

Lumpini Ville On Nut-Lat Krabang

Project progress as of
31 August 2014
 
Description Forecast/Actual Complete %
Piling Works 3 % 3 %
Structural works 30 % 30 %
Architectural Works 41 % 41 %
Electrical Works 12 % 12 %
Plumbing Works 7 % 7 %
 Elevator Works  2 % 2 %
 Cabinet Works  5 % 5 %
Summary 100 % 100 %