Lumpini Suite Phetchaburi - Makkasan
ความคืบหน้าโครงการ

Lumpini Suite Phetchaburi - Makkasan

Project progress as of
15 July 2018
 
Description Forecast/Actual Complete %
Piling Works 5 % 5 %
Structural works 32 % 30 %
Architectural Works 31 % 20 %
Electrical Works 11 % 7 %
Plumbing Works 6 % 4 %
Elevator Works 2 % 1 %
Cabinet Works 10 % 3 %
Air Conditionner Works 3 % 1 %
Summary 100 % 71 %
























 