Lumpini Suite Phetchaburi - Makkasan
ความคืบหน้าโครงการ

Lumpini Suite Phetchaburi - Makkasan

Project progress as of
15 January 2018
 
Description Forecast/Actual Complete %
Piling Works 6 % 5.42 %
Structural works 32 % 9.70 %
Architectural Works 27 % 1.17 %
Electrical Works 12 % 1.07 %
Plumbing Works 7 % 0.65 %
Elevator Works 2 % 0.00 %
Cabinet Works 11 % 0.01 %
Air Conditionner Works 3 % 0.00 %
Summary 100 % 18.02 %










 
Perspective

Perspective

Structural work of the flooring on the 10th floor

Structural work of the flooring on the 10th floor