Lumpini Seaview  Jomtien
ความคืบหน้าโครงการ

Lumpini Seaview Jomtien

Project progress as of
15 September 2014
 
Description Forecast/Actual Complete %
Piling Works 7% 7%
Structural works 27% 27%
Architectural Works 34% 34%
Electrical Works 15% 15%
Plumbing Works 10% 10%
 Elevator Works  3% 3%
 Cabinet Works  4% 4%
Summary 100 % 100 %