Lumpini Seaview Cha-Am (B)
ความคืบหน้าโครงการ

Lumpini Seaview Cha-Am (B)

Project progress as of
15 September 2017
 
Description Forecast/Actual Complete %
Piling Works 6 % 6 %
Structural works 31 % 31 %
Architectural Works 28 % 28 %
Electrical Works 13 % 13 %
Plumbing Works 10 % 10 %
 Elevator Works  3 % 3 %
 Cabinet Works  6 % 6 %
Air Conditionner Works 3 % 3 %
Summary 100 % 100 %*
Note *It is the only progress of Building B.



























 