Lumpini Place Suksawat-Rama 2
ความคืบหน้าโครงการ

Lumpini Place Suksawat-Rama 2

Project progress as of
28 February 2015
 
Description Forecast/Actual Complete %
Piling Works 7 % 7 %
Structural works 31 % 31 %
Architectural Works 36 % 36 %
Electrical Works 12 % 12 %
Plumbing Works 8 % 8 %
 Elevator Works  2 % 2 %
 Cabinet Works  4 % 4 %
Summary 100 % 100 %