Lumpini Place Borom Ratchachonni-Pinklao
ความคืบหน้าโครงการ

Lumpini Place Borom Ratchachonni-Pinklao

Project progress as of
15 December 2015
 
Description Forecast/Actual Complete %
Piling Works 5.15% 5.15%
Structural works 31.57% 31.57%
Architectural Works 32.26% 32.26%
Electrical Works 12.79% 12.79%
Plumbing Works 8.11% 8.11%
 Elevator Works  1.39% 1.39%
 Cabinet Works  8.73% 8.73%
Summary 100 % 100%
 