Lumpini ParkBeach Cha-Am
ความคืบหน้าโครงการ

Lumpini ParkBeach Cha-Am

Project progress as of
31 March 2016
 
Description Forecast/Actual Complete %
Piling Works 3% 3%
Structural works 16% 16%
Architectural Works 28% 28%
Electrical Works 14% 14%
Plumbing Works 8% 8%
 Elevator Works  2% 2%
 Cabinet Works  26% 26%
Air conditionner Works 3% 3%
Summary 100% 100%