Lumpini Park Nawamin-Si Burapha
ความคืบหน้าโครงการ

Lumpini Park Nawamin-Si Burapha

Project progress as of
15 January 2016
 
Description Forecast/Actual Complete %
Piling Works 5 % 5 %
Structural works 30 % 30 %
Architectural Works 33 % 33 %
Electrical Works 14 % 14 %
Plumbing Works 10 % 10 %
 Elevator Works  3 % 3 %
 Cabinet Works  5 % 5 %
Summary 100 % 100%