Lumpini Park Beach Cha-am2
ความคืบหน้าโครงการ

Lumpini Park Beach Cha-am2

Project progress as of
31 October 2017
 
Description Forecast/Actual Complete %
Piling Works 2 % 2 %
Structural works 14 % 14 %
Architectural Works 49 % 49 %
Electrical Works 11 % 11 %
Plumbing Works 7 % 7 %
Elevator Works 1 % 1 %
Cabinet Works 14 % 14 %
Air Conditionner Works 2 % 2 %
Summary 100 % 100 %






 