Lumpini Park Phetkasem 98  Phase  2
ความคืบหน้าโครงการ

Lumpini Park Phetkasem 98 Phase 2

Project progress as of
15 January 2018
 
Description Forecast/Actual Complete %
Piling Works 3 % 3 %
Structural works 31 % 31 %
Architectural Works 37 % 37 %
Electrical Works 14 % 14 %
Plumbing Works 8 % 7 %
 Elevator Works  2 % 1 %
 Cabinet Works  5 % 3 %
Summary 100 % 96 %











 