Lumpini ville onnut-pattanakarn
ความคืบหน้าโครงการ

Lumpini ville onnut-pattanakarn

Project progress as of
31 October 2014
 
Description Forecast/Actual Complete %
Piling Works 5% 5%
Structural works 27% 27%
Architectural Works 36% 36%
Electrical Works 16% 16%
Plumbing Works 8% 8%
 Elevator Works  2% 2%
 Cabinet Works  6% 6%
Summary 100 % 100 %